Bastrop County data centers

The data centers rising over Bastrop County

Bastrop County — specifically the Cedar Creek corridor along FM 535, ~20–30 miles southeast of Austin — has become one of Texas’s hottest data-center markets. The county has a 12-month data-center moratorium in effect through February 2027 and hired PFM Group Consulting to study the fiscal impact. Below is every known project, with the numbers that are actually published (and clear notes where they are not). The same fiber backbone feeding these campuses is what’s bringing gigabit internet to your county road.

Map centered on Cedar Creek. Project addresses: 8001 Wolf Ln, 6752/6682/6402 FM 535, and 382 Earl Callahan Rd (all 78612). Amber dot = land only / figures unverified; teal dot = confirmed project.

EdgeConneX — Cedar Creek Campus #1 (AUS02)

Under construction
Operator
EdgeConneX Inc. (Herndon, VA) — anchor tenant CoreWeave; Rackspace named in early reporting
Location
8001 Wolf Lane / 6752 FM 535, Cedar Creek (FM 535 & Wolf Lane) · ~30.139°N, −97.565°W
Size
~112–140 acres (sources differ); 4 buildings planned; first building 578,000 sq ft, two-story
Power capacity
First building up to 96 MW; campus 384 MW planned (4 × 96 MW) — CONFIRMED
Power source
Grid (ERCOT); no on-site generation reported
Water use
Not disclosed
Investment
$440M first building; ~$1.44B campus total
Jobs
~60 permanent (~$5.8M annual payroll)
Timeline
Construction began Aug 2025; first building ~Aug 2026
Tax
10-yr, 75% property-tax abatement on value above 2024 base (approved Dec 2024)

EdgeConneX — Cedar Creek Campus #2 (EDCAUS11–14)

Filed / planned
Operator
EdgeConneX Inc.; tenants not publicly identified
Location
6682 & 6402 FM 535, Cedar Creek — adjacent to Campus #1 (~30.13°N, −97.56°W, approx.)
Size
Reporting conflicts: 951 acres across two parcels (Community Impact) vs. 4 buildings ~730,000 sq ft each / ~2.9M sq ft (DCD); 2 buildings now + up to 7 future phases
Power capacity
Not disclosed — UNVERIFIED (no MW figure published)
Power source
Not disclosed
Water use
Not disclosed
Investment
~$700M first two buildings; up to ~$2.8B for four ($700M/building)
Timeline
EDCAUS11&12: start Jun 30 2026 → done Dec 31 2028. EDCAUS13&14: start Sep 1 2026 → done Mar 31 2029

Pacifico Energy “Cedar Creek Campus” (Anthropic-linked)

Under review
Developer
Pacifico Energy LLC + BlackChamber Partners. Anthropic reported in lease talks (Aug 2026) — UNVERIFIED, not finalized
Location
382 Earl Callahan Road, Cedar Creek 78612 — ~7 mi SE of the EdgeConneX campuses (~30.04°N, −97.45°W, est.)
Size
2,842 acres (~4.4 sq mi); building sq ft not disclosed
Power capacity
~490 MW data-center IT load + a 710 MW on-site natural-gas power plant — CONFIRMED
Power source
On-site natural gas, delivered directly to the campus, bypassing the local grid (island microgrid)
Water use
Not disclosed (residents formally requesting groundwater studies)
Investment
~$2.24B (power facility)
Jobs
25 permanent (~$6.2M annual payroll)
Timeline
Gas-plant construction possibly Q3 2026; operational target 2028
Controversy
Chapter 312 & JETI tax-break requests WITHDRAWN Aug 20 2026 after resident pushback; company says it will pay full property taxes. Neighbor concerns: air quality, groundwater, noise, light, traffic, the gas plant. Change.org petition active

Amazon Data Services — Cedar Creek land

Land acquired; no announced project
Owner
Amazon Data Services Inc. (AWS)
Location
Cedar Creek, ~3 mi SW of EdgeConneX (formerly the planned “Creekside” community; bought from CTX Capital Partners, closed May 1 2026)
Size
1,229 acres (some outlets: 1,300+)
Status
No public filing, timeline, capacity, power, water, jobs, or investment announced — UNVERIFIED; do not assume figures

Regional context

Regional context — Sandow Lakes / “Stargate” (Milam County, NOT Bastrop)

Milam County — regional context
Why it's here
The user often-conflated Alcoa/Sandow site is in Milam County (Rockdale, ~70 mi NE of Austin), not Bastrop — included only as regional context
Project
OpenAI “Stargate,” built/operated by SB Energy (SoftBank), with OpenAI/Oracle/SoftBank; on the ~33,000-acre Sandow Lakes Ranch
Power capacity
1.2 GW (1,200 MW) planned — CONFIRMED; largely on-site generation + storage; first building ~Oct 2026

The bottom line on power

Only two hard megawatt figures are public: EdgeConneX Campus #1 at 384 MW planned, and the Pacifico/Anthropic-linked campus at ~490 MW of IT load plus a 710 MW on-site gas plant. Campus #2 and the Amazon land have no published capacity. No water-use figure has been published for any Bastrop project — that gap is itself a live local controversy. We don’t invent numbers; where it says “not disclosed,” it means exactly that.